Renovating a rental between tenancies in Portugal: what to fix first

By Kellogg Fairbank · Co-founder of remodel · Last updated November 2026
Painter and property manager preparing a vacant rental apartment for the next tenancy, renovating a rental between tenancies in Portugal, 2026
Start with defects that affect safe use, security, water ingress and essential services. Then choose improvements that fit the available time, with a buffer for checks and corrections before handover. Give everything else a place in a later maintenance plan.

The outgoing tenant returns the keys on Friday. The next tenancy starts in three weeks. The apartment needs painting, a bathroom tap drips, and the bedroom has a damp patch behind the wardrobe. There is also a kitchen you have wanted to update for years.

3
Priority tiers: urgent repairs, improvements while vacant, and work that can wait
3 weeks
Illustrative vacancy: investigate, repair, then test, inspect and correct
IVA
Ask trades to include it, with protection, waste removal, making good and testing
One brief
remodel can match you with vetted and verified contractors for the work you need

What's in this guide

  • Photograph and log every defect on day one, with location, symptom and who will handle it
  • Items are sorted into urgent repairs, improvements while vacant, and work that can wait
  • Leaks and damp are investigated first, before any redecorating is scheduled
  • A three-week vacancy runs investigate, repair, then test, inspect and clean in the final week
  • One decision-maker approves scope and budget so the fixed handover date holds

Start with a documented inspection


Photograph every room as soon as you regain access, record each defect with its location, symptom, required outcome and who will handle it.

Walk through the property as soon as you regain access. Photograph each room, record defects and test the normal operation of fittings and appliances where appropriate. Ask the relevant trade to investigate anything that needs specialist assessment.

For every item, record the location, symptom, required outcome and who will assess or carry out the work.

Vague brief

“Bedroom wall needs painting”

Useful brief

“Investigate staining behind the bedroom wardrobe, identify the cause and propose the repair before redecorating.”

Important

Keep the works record separate from decisions about responsibility for damage or deductions from a deposit. The contractor needs an accurate scope and access arrangements to price and schedule the job.

Divide the scope by what the next tenant needs


Sort every item into urgent repairs and investigations, improvements worth making while vacant, and work that can wait for a planned refurbishment.

PriorityExamplesHow to handle it
Act first
Urgent repairs and investigations
Active leaks, insecure doors, suspected electrical faults, failed hot water, damaged sanitary fittings and unexplained damp.Arrange assessment first. Agree the repair and testing needed before the property can be handed over.
While vacant
Improvements worth making while vacant
Painting, repairing damaged flooring, replacing worn silicone where appropriate, servicing shutters, improving storage and replacing unreliable appliances.Include work that has a clear scope, available materials and a realistic place in the programme.
Later
Work that can wait
Replacing a functional kitchen for appearance, decorative lighting changes, bespoke joinery and a bathroom layout change without an immediate need.Record it for a planned refurbishment unless the vacancy period and budget support a larger project.

Note

The same task can fall into different categories. A loose cupboard handle is a small repair. A wall unit coming away from its fixings needs prompt attention. Ask trades to describe the condition they find and the outcome they recommend.

Fix the cause before scheduling the finish


Leaks and damp can disrupt a short programme, so have them assessed early and agree what must be confirmed before any redecorating starts.

Leaks and damp can disrupt a short programme because investigation, repair and drying may affect later work. Ask for an assessment early and have the contractor identify what can be confirmed during the visit and what requires opening up.

If the bedroom wall is damp, explain when the staining appeared, what sits behind or above it and whether it changes with rain or occupancy. Agree who will investigate, how the findings will be reported and what conditions must be met before redecorating.

Important

If you are replacing a shower screen or vanity, ask the contractor to check the adjacent finishes and connections before ordering. A small upgrade may expose a repair that changes the scope.

A sample scope for a three-week vacancy


A sample two-bedroom scope shows how each item gets a defined scope, a priority and an acceptance check before the fixed Friday handover.

Illustrative example: a two-bedroom apartment. The incoming tenant’s handover is fixed for Friday at the end of week three. The programme depends on the initial findings and confirmed availability.

ItemPriority and scopeAcceptance check
Dripping kitchen tapInspect the fitting and connections. Repair or replace with the approved model.Plumber checks operation and connections after completion.
Bedroom damp patchInvestigate before painting. Report the likely cause, evidence and proposed next step.Property manager reviews the findings and any repair. Decoration proceeds only when the surface is suitable.
Front door lockCheck security and operation. Replace the cylinder if specified by the owner.Door locks and opens normally. Keys are counted and recorded.
Bathroom extractorAssess poor operation and price the required repair or replacement.Contractor verifies operation after the work.
PaintingPrepare and paint agreed dry rooms, doors and trims. Exclude the affected bedroom wall until assessed.Check coverage, preparation, edges and protection of retained surfaces.
Bedroom floor damageInspect and carry out an agreed local repair if feasible.Check the repair and transition with the surrounding floor.
Appliance replacementReplace an unreliable washing machine with an approved, available model. Include delivery, installation and removal.Installer checks connections and completes the appropriate functional checks.
Full kitchen replacementDefer for a later planned vacancy.Add to the longer-term improvement schedule.
Final clean and inspectionBook after dusty work and before handover.Photograph each room and record outstanding items for correction.

Important

If the first inspection identifies a major defect, review the scope and handover plan immediately. Ask the responsible professional what needs resolving before occupation, then discuss the implications with the incoming tenant and appropriate advisers.

Work backwards from the handover date


Investigate and secure essentials first, complete repairs and agreed improvements next, and leave the final week for testing, snagging, corrections and cleaning.

For the sample apartment, the three weeks might be organised as follows.

01
Investigate and secure the essentials

Complete the site visits, approve urgent repairs and confirm materials. Resolve the lock and tap early. Investigate the damp and extractor so their findings can inform the remaining programme.

02
Complete repairs and agreed improvements

Carry out the work that affects finishes, then proceed with painting in areas ready for decoration. Install confirmed items and record any change to cost or timing as soon as it arises.

03
Test, inspect and correct

Set an internal completion target early enough to allow a snagging visit, corrections and cleaning. Keep the final handover appointment separate from the builder’s completion target.

Note

The schedule should account for drying, product curing requirements and delivery availability. Ask each trade to confirm those dependencies when accepting the programme.

Need the right trades within the vacancy?
remodel can introduce suitable contractors for a defined job, matched on location, specialism, project size, availability and language.
Tell us about the job

Brief trades with a fixed finish date


Send every contractor the same scope, photos and access information, so prices are comparable and each trade can confirm it can commit.

Send every contractor the same scope, photos and access information. A clear brief makes it easier to compare prices and establish whether the team can commit.

Contractor briefRental · between tenancies
Project
Two-bedroom rental apartment in [location], vacant between tenancies.
Dates
Access is available from [date]. Works must be ready for inspection by [date]. Tenant handover is [date]. Please confirm your earliest start, expected duration and availability for any corrections.
Scope
Please price each item in the attached list separately. Identify any investigation required before a repair can be priced. Include protection, removal of waste, making good, testing and IVA.
Materials
Please identify who supplies each item and confirm availability before scheduling installation. Send alternatives for approval if the specified product is unavailable.
Access and coordination
Keys are held by [contact]. Building access, parking, lift protection and working arrangements are [details]. [Name] coordinates the trades and confirms when each work area is ready.
Changes
Send photos, the proposed work, additional price and programme effect to [approver] before proceeding with changes.
Handover
Include a completion visit, functional checks relevant to your work, and delivery of invoices, product information, warranties and keys as applicable.

For plumbing or electrical concerns, describe the symptoms and request assessment by the appropriate professional. Let the trade specify the technical remedy after inspection.

Give one person authority to make decisions


Name one owner or property manager to approve scope and budget, and a coordinator when several trades are involved, so decisions do not stall the programme.

A short vacancy can lose days while a contractor waits for a tap model, paint colour or repair approval.

Name one owner or property manager who can approve the scope and budget, and give contractors a reliable contact method. Agree how urgent findings will be escalated and when a decision is needed to preserve the programme.

If several trades are involved, nominate a coordinator. Confirm who books the sequence, checks access and follows up when one task delays another. Record approved changes with their cost and timing so the final invoice can be checked against the agreed work.

Check the property before the tenant arrives


Inspect against the agreed scope, collect test and completion information, record remaining defects with owners and dates, then clean and count keys.

Use the agreed scope as the inspection list. Check the completed repairs and ask for the relevant trade’s test or completion information.

Walk through

DoorsWindowsShuttersTapsDrainageAppliancesHot water

Record remaining defects with photographs, an assigned contractor and a correction date. Finish with cleaning, removal of surplus materials and a key inventory. Keep a photographic record of the property’s condition at handover.

Frequently asked questions


Conclusion


We can help match you with vetted and verified contractors for the work you need. If several trades or a larger refurbishment need coordination, we can also discuss independent project management.

Free contractor matching · nationwide

You will know what is happening, who is responsible and what decisions are required.

Tell us when the property becomes vacant.
Tell remodel where the property is, when it becomes vacant and the next tenant’s handover date. Send photographs and a list of urgent repairs and proposed improvements.
Request contractor matching for a rental
Kellogg Fairbank
Kellogg Fairbank
Co-founder, Remodel · Cascais, Portugal

Kellogg is a former payments executive turned entrepreneur, with a family background in real estate. He has spent the past year bringing that experience to the Portuguese property market, and co-founded remodel to apply the same rigor to how contractors are vetted.

This guide gives general information and is not legal, technical or engineering advice. Confirm the requirements for a specific property with a local architect, engineer or the câmara municipal. Vetting supports informed selection; it does not guarantee future performance or replace project-specific checks, contracts and oversight. You contract directly with the appointed professionals and contractors. The photo is illustrative and does not show a remodel project. Regulatory information checked 5 November 2026.