Renovation Types · Cost Guide

Kitchen Refit in Portugal: Cost, Timeline, and What's Actually Included in 2026

By Pascal Niggli · Co-founder of remodel · Last updated July 2026
Kitchen Refit in Portugal: Cost, Timeline, and What's Actually Included in 2026
A kitchen refit in Portugal costs €8,000–€48,000, from about €8,000–€30,000 for a standard kitchen to €28,000–€48,000 for a full-spec refit in a 120m² home, and takes 8–14 weeks from quote acceptance to handover. Cabinets, worktops, plumbing and electrical rerouting, tiling, and appliances are the biggest cost drivers, and quotes for the same scope routinely vary by 30–50% between contractors, which is why Remodel checks every quote against regional project data before you see it.

What's in this guide

  • A kitchen refit in Portugal runs €8,000–€48,000 including materials, labour, and permits
  • Cabinet fabrication lead time alone can run 4–6 weeks, driving the 8–14 week total timeline
  • Cosmetic refits that keep the existing footprint typically don't require a building permit (licenciamento)
  • Remodel checks every kitchen refit quote against regional project data before it reaches you
  • Quote variance of 30–50% for identical scope is the biggest overpayment risk for foreign owners

How Much Does a Kitchen Refit Cost in Portugal?


€8,000–€48,000 depending on size and finish, including materials, labour, and permits, checked against regional project data so you know if you're being quoted fairly.

The range reflects finish level as much as scope. A budget refit with laminate worktops and stock cabinets sits near the lower bound; stone worktops and custom joinery push toward €48,000 and above.

Line itemTypical range
Cabinets (stock)€6,000–€11,000
Cabinets (custom joinery)€12,000–€22,000
Worktops (laminate)€800–€1,800
Worktops (stone)€2,500–€6,000
Plumbing & electrical rerouting€2,500–€5,500
Tiling (floor + splashback)€1,800–€4,200
Appliance integration€3,000–€8,000
Labour€10,000–€18,000
A Remodel quote itemises every one of these lines separately, and we flag anything that sits well above the regional median for that trade.

What Drives the Cost of a Kitchen Refit?


Cabinet material and worktop stone selection drive most of the cost variance, followed by whether plumbing and electrical lines get relocated or reused in place.

Reusing the existing plumbing and electrical footprint keeps a refit near the lower end. Relocating a sink or hob, even within the same room, adds €1,500–€3,500 in rerouting cost and can extend the timeline by 1–2 weeks. Stone worktops (quartz, granite) cost 3–4× laminate but are the most requested upgrade among our Cascais and Lisbon clients.

How Long Does a Kitchen Refit Take?


8–14 weeks from quote acceptance to handover, including 4–6 weeks of cabinet fabrication lead time that runs in parallel with demolition and rough-in work.

Custom joinery is the long pole in almost every kitchen timeline. The final 2–3 weeks cover installation, tiling, appliance integration, and snagging. Delays most often come from supplier lead times on imported appliances, not the construction work itself.

Planning a Kitchen Refit?
Planning a kitchen refit? We match you with a vetted, English-speaking contractor and get you a competitive itemised quote, completely free.
Request a quote for your kitchen refit →

Do I Need a Permit to Refit a Kitchen in Portugal?


Usually not, if the refit keeps the existing footprint and doesn't move load-bearing walls or shared risers. Moving the kitchen to a different room does require a permit.

Relocating a kitchen to a different room, altering the façade, or changing the building's use-type triggers a building permit (licenciamento) under RJUE from the câmara municipal. If the property sits in a condominium, moving plumbing or gas connections within the unit usually only requires notifying the administration, but this varies by building and should be confirmed before demolition begins.

Planning a kitchen refit? We match you with a vetted, English-speaking contractor and get you a competitive itemised quote, completely free.

Request a quote for your kitchen refit →

How Remodel Runs a Kitchen Refit Project


We scope the refit in English, match you with a vetted contractor experienced in kitchens in your area, and check the returned quote against regional project data before you decide.

Tell us what you need

Photos, dimensions, desired finishes, and budget, under two minutes, no account required. We flag likely permit requirements at this stage.

We find the right contractor

One contractor from our network with real kitchen refit experience in your area, not a list to sift through ourselves.

You get a proper quote

An itemised, room-by-room quote you can actually understand, checked against what similar kitchens cost in your region. If it doesn't feel right, tell us, we'll find a different match.

Frequently Asked Questions


Conclusion
A kitchen refit in Portugal is a €8,000–€48,000, 8–14 week project. The two biggest risks are unchecked quotes and unverified contractors, both of which we're built to remove.
Request a quote for your kitchen refit

Related reading: Bathroom Rebuild · Full House Renovation · Outdoor & Landscaping Renovation

See the full Lisbon-specific cost breakdown →

See the service page: request a kitchen refit quote →

Pascal Niggli
Pascal Niggli
Co-founder, Remodel · Cascais, Portugal

Pascal is the co-founder of remodel. Originally from Switzerland, he has lived in Portugal for several years and has first-hand experience with the permit, VAT, and contractor issues property owners run into. He built remodel to be the resource he wished existed when he started.

Cost ranges are indicative and based on completed projects across Portugal. Actual costs vary by property condition, scope, materials, and contractor. Last updated: July 2026.