Managing a Portuguese property renovation on behalf of a family office
By Kellogg Fairbank · Co-founder of remodel · Last updated November 2026
The contractor in Portugal needs a decision. The architect has proposed a revised detail. The family-office adviser is in London, the owner is travelling and the local project manager is waiting for approval. Who can authorise the change, and what exactly are they authorising?
Start with the legal client and the owner’s representative
Identify the person or entity commissioning the work and signing each appointment. The family principal, property-owning company and family office may have different roles.
Then name one day-to-day owner representative. This might be an asset manager or adviser who consolidates instructions, coordinates internal approvals and communicates the owner’s decisions.
Record:
- The contracting entity and authorised signatories.
- The owner’s nominated representative and alternate.
- Which decisions are delegated and which remain reserved.
- Who can issue contractual instructions.
- Who approves invoices and who releases payment.
- How absence, travel and urgent matters will be handled.
Have the relevant advisers confirm that delegations and signatory arrangements are properly documented.
Distinguish coordination, technical review and approval
Coordinates the team, tracks progress, maintains records and prepares recommendations within an agreed appointment.
Accepts or advises on a proposed detail. This does not approve its commercial consequences.
Approves expenditure and reserved decisions, through the named authorised person.
A local project manager can coordinate the team, track progress, maintain records and prepare recommendations within an agreed appointment. The title alone does not establish power to approve extra expenditure, change a design or issue a contractual instruction.
Similarly, an architect’s technical acceptance of a proposed detail does not automatically approve its commercial consequences. The contractor also needs to understand how an instruction becomes valid under the agreed contract.
A sample responsibility matrix
The following is an illustrative allocation for an owner-side oversight arrangement. Adapt it to the project’s procurement structure, contracts and professional appointments.
The authorised decision-maker for the commissioning entity.
The nominated family-office representative.
Neither label assumes authority that has not been granted.
Scroll sideways to see all five parties
| Activity | Owner | Adviser | Architect | Project manager | Contractor |
|---|---|---|---|---|---|
| Set objectives and overall budget | Approves | Consolidates requirements | Advises on design implications | Coordinates initial plan | Provides buildability and pricing input when engaged |
| Develop design and specification | Approves key requirements | Coordinates owner feedback | Leads architectural design within appointment | Tracks decisions and dependencies | Reviews construction implications within agreed role |
| Coordinate specialist input | Authorises appointments | Reviews recommendations | Identifies design disciplines needed | Coordinates agreed appointments and information | Identifies construction queries |
| Assess contractor proposals | Approves selection | Reviews recommendation | Reviews design scope and qualifications | Coordinates comparison and exclusions | Submits scope, price and programme |
| Review a proposed change | Approves reserved decisions | Approves only within delegation | Reviews design and technical effects | Logs change and consolidates cost and time assessment | Prices and explains construction effects |
| Issue a contractual instruction | Through the named authorised person | Only if expressly authorised | Only if contractually appointed to do so | Only if contractually appointed to do so | Receives and implements valid instructions |
| Report progress and risks | Receives report | Reviews and escalates | Provides design-status input | Consolidates owner report | Supplies programme, progress and site information |
| Review payment requests | Approves as agreed | Checks internal authority and documentation | Assesses relevant matters within appointment | Coordinates verification and recommendation | Submits supported application or invoice |
| Release payment | Through authorised finance signatories | Coordinates finance process | Informed as needed | Records status | Receives payment |
| Coordinate completion and defects | Makes owner decisions on advice | Coordinates owner requirements | Reviews within appointment | Tracks checks, records and outstanding items | Completes work and remedies agreed defects |
Agree approval rules before the first variation
An approval process needs more than a financial limit.
Define which changes can be delegated, the information required and when a decision must return to the owner. A small change in price could still affect the agreed completion date, the use of the property or a feature the owner considers essential.
Useful reserved matters may include:
- Increasing the total approved budget.
- Changing the intended use or essential accommodation.
- Altering key design features or agreed finish standards.
- Accepting a material change to completion timing.
- Appointing or replacing major project participants.
- Settling disputed claims or accepting contractual concessions.
For delegated expenditure, specify both individual and cumulative limits. Several related changes should not be split into smaller requests to avoid escalation.
State whether limits include IVA and whether they permit use of contingency. Having an available reserve does not automatically authorise anyone to spend it.
Use a recorded process for changes
Consider a fictional renovation where opening up a ceiling reveals deterioration that may require additional work.
- 01Contractor reports. Sends photographs and a proposal.
- 02Project manager records. Logs the issue in the change register.
- 03Technical response. The architect or relevant engineer assesses it.
- 04Cost and programme. The contractor explains the effects on both.
- 05Owner decision. The authorised owner representative receives a recommendation for decision.
A practical change record should contain:
| Field | What to record |
|---|---|
| Reference | A unique number used in correspondence and reports |
| Reason | Concealed condition, design development, owner request or another stated cause |
| Scope | The work proposed and the current scope it changes |
| Evidence | Photographs, drawings, inspection findings and relevant correspondence |
| Technical review | Who reviewed the proposal and what remains unresolved |
| Commercial assessment | Price, tax basis, credits, assumptions and exclusions |
| Programme effect | Expected delay, dependencies and available alternatives |
| Decision | Approval, rejection, request for information or deferred decision |
| Authority | Name of approver and basis of their authority |
| Instruction | Required contractual instruction, issued by the authorised person |
| Status | Proposed, approved, instructed, completed or otherwise clearly defined |
Internal approval and contractual instruction are separate steps where the contract requires them to be. Record both.
Agree a response date and explain what happens if it is missed.
Plan for urgent issues and unavailable decision-makers
The owner may be on a flight when an issue arises. The normal approver may be unavailable for several days.
Name an alternate in advance and identify what can be escalated to them. Use Portugal time for site deadlines, with other time zones shown where useful.
For urgent safety or damage-prevention situations, agree the notification and escalation process with the relevant professionals and contractor. It should accommodate necessary immediate protective action under the applicable duties and contract, while recording what was done, by whom and why.
Urgency should be documented precisely rather than used as an open-ended approval category.
Make owner reporting useful for decisions
A weekly report should help the family office understand the position and act on the matters needing attention.
Use a consistent structure:
- 01Executive position. Overall progress, principal concerns and changes since the previous report.
- 02Programme. Completed activities, next steps and forecast milestones.
- 03Cost. Approved budget, commitments, payments, forecast final cost and remaining reserve.
- 04Changes. New requests, decisions made and outstanding assessments.
- 05Quality. Observations, specialist inspections, tests and open defects within the agreed scope of reporting.
- 06Owner decisions. Recommendation, approver and required response date.
- 07Evidence. Dated photographs and links to current documents.
If costs are still being assessed, say so. A report should distinguish a confirmed amount from an estimate and a potential exposure.
For several properties, provide a short portfolio summary with a separate report for each asset. This helps the family office identify which project needs attention without losing the underlying detail.
Connect payment approval to verification
Decide who reviews progress, who checks the invoice against the agreement and who can authorise payment.
The supporting pack should identify the relevant work, approved changes, previous payments and unresolved items. Technical assessment or certification should be performed by the person appointed and qualified for that role.
The family-office finance team then follows its own payment controls. Confirm changes to bank details through an established independent verification process.
Keep one current record of the project
Agree where approved drawings, reports, instructions and decisions are stored, and who can access them.
Practical controls include:
- Drawing revision numbers and clear status labels.
- A current decision register and change register.
- Meeting notes with named actions and deadlines.
- Written confirmation of decisions discussed on calls or site visits.
- A defined language for formal records and a process for resolving translation questions.
Messaging applications can support quick coordination. Important approvals should also be captured in the agreed project record and issued through any contractually required channel.
For a private residence, agree what photographs may show and who may receive them. Separate site-reporting access from permission to publish material externally.
Plan handover as part of oversight
Agree completion requirements early enough for the team to prepare the records and checks.
Depending on the project, the handover pack may include inspection and test records, operating instructions, warranties, approved updated drawings and a register of outstanding defects with owners and target dates.
Distinguish physical progress, technical verification, practical readiness for occupation and contractual completion. Their relationship needs to be established through the relevant professional advice and contract.
For family offices, nominate the person who will receive the property operationally. The future property manager may need system training and maintenance information even if they were not involved in construction decisions.
Questions to settle before work begins
- Who is the legal client, and who signs each appointment?
- Who represents the owner day to day, and who is the alternate?
- Which decisions are delegated, and which remain reserved?
- Who can issue contractual instructions?
- Who assesses design, technical compliance, quality and payment milestones?
- How are changes, contingency and cumulative expenditure controlled?
- What does the reporting appointment include, and how often will site visits occur?
- How will urgent issues, disputes and unavailable approvers be handled?
- What records and checks are required at handover?
Clear answers give the local team a workable route to decisions and the family office a defined basis for oversight.
Frequently asked questions