Your renovation is almost finished. What should you check before handover?

By Kellogg Fairbank · Co-founder of remodel · Last updated November 2026
Homeowner photographing a kitchen cabinet defect during a renovation handover inspection in a Lisbon apartment, Portugal, 2026
Check the completed work against the agreed scope, record defects clearly and agree how outstanding items will be resolved. Include operation and documentation alongside appearance.

The floors are uncovered, the kitchen is fitted and the contractor is talking about returning the keys. Before you move furniture in, allow time to walk through the property, check what has been delivered and collect the records you will need to look after it.

8
Areas in the room-by-room snagging checklist, from entrance to outbuildings
9
Types of handover record to collect in one folder, by room or system
Contract
Its definitions of completion, snagging, payment and handover govern the process
Your side
remodel can discuss arranging an independent handover inspection

What's in this guide

  • Book the inspection when the property is clean, complete and powered, with the contract documents to hand
  • An eight-area, room-by-room snagging checklist runs from the entrance to outbuildings
  • Each defect gets a wide photo, a close-up and one reference number
  • Nine types of handover record go into one folder organised by room or system
  • Completion and payment follow your contract, and an independent inspector can review the work

Arrange the inspection before moving day


Book the inspection when the property is clean, complete and powered, bring the contract documents, and agree who inspects and when corrections return.

Ask for the property to be sufficiently clean, accessible and complete for a meaningful inspection. Water, electricity and relevant installed systems need to be available for the agreed checks. Arrange access with the contractor and have someone present who can explain the work and operate the equipment.

Bring with you

ContractDrawingsSpecificationsApproved changesPrevious inspection reports

They give you a reference for checking quantities, models, finishes and any agreed departures from the original plan.

Note

Agree who will inspect, who will prepare the snagging list and when the contractor will return for corrections. Book a follow-up check before treating those items as resolved.

A room-by-room snagging checklist


A snagging list records incomplete, defective or incorrectly supplied work. Check each area for operation, finish and supply against the specification.

A snagging list records incomplete, defective or incorrectly supplied work. Some items are cosmetic. Others need assessment by the appropriate professional before the room or system is used.

AreaWhat to checkExamples to photograph
Entrance, hall and stairsDoor operation, locks, keys, thresholds, trims, handrails and finishes. Check that access routes are clear.A door rubbing on the floor, a loose handrail fixing, chipped threshold stone or unfinished trim.
Living and dining roomsPaint coverage, damaged surfaces, flooring, skirtings, windows, shutters and agreed lighting operation.Open flooring joints, paint on fittings, a damaged board or a window that does not close properly.
KitchenSupplied models against the specification, cupboard and drawer operation, worktop condition, seals and appliance installation. Ask the installer to demonstrate relevant functions.A chipped worktop edge, misaligned doors, a loose handle or visible moisture inside the sink cupboard.
Bathrooms and WCTaps, hot water, flushing, drainage, shower screen operation, seals, tile damage and extractor operation. Have the contractor demonstrate the shower and check adjacent areas.Water collecting after use, a gap in sealant, a cracked tile or damp appearing outside the shower.
Bedrooms and fitted storageDoors, wardrobes, shelves, sockets, switches, windows and agreed finishes.Drawers catching, missing shelf supports, scratches on joinery or incomplete painting behind a door.
Utility and service areasAccess to valves and equipment, labels, appliance connections and operating instructions.An unidentified valve, inaccessible service panel, missing label or visible drip.
Terraces, balconies and garden worksAgreed finishes, thresholds, drainage points, external lighting and the condition of retained areas.Damaged paving, blocked outlets, unfinished edges or visible ponding requiring investigation.
Garage and outbuildingsDoors and controls, lighting, agreed services, finishes and removal of waste.Damaged door tracks, incomplete fittings, debris or water staining.

Note

These are observations to record. Ask the appropriate trade or inspector to assess the cause and remedy where it is unclear.

Finishes in normal use

Walk through in daylight and with the installed lights on. Check floors before rugs and furniture conceal them. Open cupboards, drawers, doors and shutters through their normal range.

Compare disputed finishes with the agreed specification, sample or applicable assessment criteria. If an item needs specialist review, record that requirement in the list.

Systems as well as switches

Ask the contractor and relevant installers to demonstrate the hot water, heating, cooling, ventilation, appliances and controls included in the works. Record any system that could not be demonstrated and arrange the appropriate follow-up.

Important

A light turning on does not establish the condition of the electrical installation. Ask for the relevant testing and completion records and use qualified professionals for specialist checks.

Important

A final walk-through cannot directly inspect waterproofing, pipework or structure already concealed. Review the available photographs, test results and earlier stage reports. Record missing evidence and ask the inspector what further assessment is appropriate.

Photograph defects so the contractor can find them


Pair a wide location photo with a close-up under one reference number, describe what you observed, and leave the diagnosis to the person assessing it.

For each item, take a wide photograph showing its location and a close-up showing the issue. Give both images the same reference number. Where useful, include a ruler or another suitable scale without damaging the finish.

A useful log entry might read

RefObservationAction and responsibilityFollow-up
K-03Kitchen drawer beside the oven catches on the adjacent front when opened. Photos K-03a and K-03b.Builder to adjust and check operation.Recheck at the agreed return visit.
B-02Moisture visible at the shower screen’s outer corner following the demonstration. Photos B-02a and B-02b.Builder to arrange assessment by the relevant installer and propose a remedy.Repeat the appropriate check after repair.
W-01Bedroom window does not latch during normal operation. Photos W-01a and W-01b.Window installer to investigate and correct.Owner or inspector to verify operation.

Describe what you saw

“Moisture appeared below the connection” gives the plumber useful information.

Leave the diagnosis

Keep the technical diagnosis with the person assessing the work.

For video, record a short clip of movement, noise or an intermittent fault, together with the location and circumstances.

Not sure who is checking the work on your side?
Independent project management gives you coordination and oversight alongside your existing contractor, from progress checks to the handover record.
Discuss your project

Collect the handover records


Ask for one digital folder organised by room or system, covering contract, products, warranties, testing, concealed work, official records, maintenance and access.

Ask for a digital folder organised by room or system, with a list of anything outstanding.

Financial
Contract and financial record

The agreed scope, approved changes, invoices and a reconciliation of payments and remaining sums.

Equipment
Product information

Manuals, model numbers, serial numbers and supplier details for appliances and installed equipment.

Cover
Warranties and guarantees

Documents supplied by the contractor and manufacturers, relevant dates, maintenance conditions and the contact for reporting a problem.

Systems
Testing and commissioning

Relevant electrical, plumbing, heating, cooling and other specialist records applicable to the work, including unresolved tests.

Hidden work
Drawings and concealed-work information

Updated drawings where included or applicable, service routes, valve locations and photographs taken before surfaces were closed.

Official
Municipal and professional records

Documents applicable to the completed works, identified with the architect or responsible professional.

Upkeep
Maintenance and finishes

Paint references, tile and grout details, cleaning instructions, service intervals and spare materials agreed in the scope.

Access
Access items

Keys, remotes, access codes and instructions for controls. Agree how credentials will be transferred securely.

Snagging
Inspection record

The dated snagging list, responsibility for each action and the agreed verification process.

Important

A manufacturer’s warranty and the contractor’s responsibilities can involve different parties and terms. Keep both sets of records and clarify where to report each type of issue.

Link the inspection to the agreed completion and payment process


Read your contract’s definitions of completion, snagging, payment and handover, and compare the contractor’s completion claim with the recorded outstanding items.

Review the contract’s definitions of completion, snagging, payment and handover. Compare the contractor’s completion claim with the recorded work and outstanding items.

remodel’s guide to Portuguese renovation contracts explains the matters to agree in writing, including scope, changes and snagging. The guide to milestone payments and independent inspections shows how inspections can be connected to progress payments.

Legal basis

Apply the payment arrangements agreed for your project. If completion or payment is disputed, obtain advice on the contract before taking action. Record any agreed arrangements for outstanding work, access and verification in writing.

What an independent handover inspection can add


An independent inspector reviews the work against the agreed scope, identifies visible defects and flags issues that need specialist investigation.

An independent inspector can provide a structured review against the agreed scope, identify visible defects and help distinguish issues needing specialist investigation. Confirm their qualifications, inspection scope, access needs and report format before appointment.

Ask what systems they will check, what documentation they will review and whether a return visit is included. Share earlier reports and concealed-work photographs so the assessment has the available project history.

Note

After corrections, update each item with evidence of the completed work and the person who checked it. Keep unresolved matters visible in the handover record.

Frequently asked questions


Conclusion


We can discuss arranging an independent handover inspection and the appropriate expertise for your project.

You will know what is happening, who is responsible and what decisions are required.

Tell us when the contractor expects to finish.
Tell remodel where the property is, what work has been carried out and when the contractor expects to finish. Share the scope, available drawings and any concerns you want reviewed.
Discuss an independent handover inspection
Kellogg Fairbank
Kellogg Fairbank
Co-founder, Remodel · Cascais, Portugal

Kellogg is a former payments executive turned entrepreneur, with a family background in real estate. He has spent the past year bringing that experience to the Portuguese property market, and co-founded remodel to apply the same rigor to how contractors are vetted.

This guide gives general information and is not legal, technical or engineering advice. Confirm the requirements for a specific property with a local architect, engineer or the câmara municipal. Vetting supports informed selection; it does not guarantee future performance or replace project-specific checks, contracts and oversight. You contract directly with the appointed professionals and contractors. The photo is illustrative and does not show a remodel project. Regulatory information checked 5 November 2026.