How to plan a commercial fit-out in Portugal: from lease review to opening day

By Kellogg Fairbank · Co-founder of remodel · Last updated November 2026
Architect and tenant reviewing a floor plan in an empty Lisbon commercial space.
The first decision is whether the space can support the way you plan to operate. Check that before committing to a lease, a construction budget or an opening date.

A commercial space can look ready for your business at the first viewing. Then you discover the electrical supply may need upgrading, the air-conditioning equipment needs a location the landlord hasn’t agreed to, or the rent starts well before you can open.

A commercial fit-out is the work that makes a leased space ready for your business. It might involve a light office refurbishment or a full build-out from an empty shell. The first decision is whether the space can support the way you plan to operate. Check that before committing to a lease, a construction budget or an opening date.

5 stages
From first viewing and lease review to handover
3 dates
Access, rent start and opening, on one schedule
4 roles
Tenant, landlord, design team and contractor
Opening day
Plan backwards from it

What's in this guide

  • A first-viewing checklist covers use, exits, power, ventilation, frontage and handover condition
  • Civil Code Article 1074 makes tenant works depend on the lease or written landlord consent
  • Tenant, landlord, design team and contractor each decide different things before a fixed price
  • Quotes compare on one package, with landlord works, allowances and VAT shown separately
  • Access, rent start and opening dates share one schedule, planned backwards from opening

Take this checklist to your first viewing


Bring a short brief, record what you can see, and end the viewing with three lists: what works, what needs checking, what needs agreement.

Bring a short brief with your intended activity, expected number of staff and customers, equipment needs, operating hours and target opening date. Ask for a floor plan and permission to take photos. At this stage, record what you can see and ask who can verify the rest.

Two people measuring the width of a commercial entrance with a tape measure.
Check at the viewingWhat to record or ask for
Existing use and layoutAsk for the latest available plans and records showing the current authorised use. Note where your desks, stockroom, kitchen or customer area would go.
Entrance, circulation and exitsPhotograph steps, narrow doors, corridors, exits and toilets. Flag any route customers or staff would need to use that looks difficult. Ask the design team to assess accessibility and fire safety.
Power and dataAsk what electrical capacity is available and where the distribution board and internet connection are. List the equipment you’ll run so an engineer can compare the demand with the available supply.
Water, drainage and ventilationNote where water and drainage are visible. Ask what ventilation or air conditioning serves the unit and where new ducts, outdoor units or extraction could go.
Frontage and signagePhotograph the shopfront or entrance. Ask who controls changes to glazing, signs, shutters and external equipment.
Deliveries, waste and building rulesWalk the route from street to unit. Ask about loading, lifts, working hours, waste storage and access to shared areas during construction and after opening.
Condition and handoverRecord visible damage, damp and equipment left behind. Ask what the landlord will repair or remove and what condition the unit will be in when you get the keys.

End the viewing with three lists: what works for your business, what needs a technical check and what depends on someone else’s agreement. If your restaurant depends on an extraction route through a shared part of the building, for example, ask your design team to assess the route and your landlord to establish who can authorise it.

Agree what the lease allows before you sign


Have a Portuguese commercial property lawyer review the lease with your fit-out proposal, and agree handover, works, rent and end-of-lease terms before you sign.

Ask a Portuguese commercial property lawyer to review the draft lease alongside the fit-out proposal. Under Portugal’s Civil Code, tenant works generally need to be permitted by the lease or authorised in writing by the landlord. Describe the proposed works clearly enough that both sides can see what they are agreeing to.

Get agreement on the points most likely to affect your budget and opening date.

Condition at handover

List the repairs or equipment removals the landlord will complete and when the unit will be available for surveys or works.

Works and building access

Agree which alterations are permitted, who can approve changes and who will obtain any building management or condominium consent needed for shared areas.

Rent and costs

Confirm when rent starts, whether there is a rent-free fit-out period, and who pays for items such as a supply upgrade or repairs to existing systems.

What happens if a key assumption fails

If the deal depends on a particular use, a workable extraction route or another critical item, ask your lawyer whether to negotiate a condition before committing.

End of the lease

Agree what can stay, what you can remove and whether you must reinstate any part of the space.

In parallel, ask the design team to verify whether the intended use and works trigger a municipal procedure. Keep three questions separate in the programme.

Three separate questions
  1. What does the lease allow?
  2. What does the municipality require for the premises or works?
  3. What does your business need to file or obtain before opening?

For a restaurant, café or bar, the government’s opening service sets out the requirement to submit a Mera Comunicação Prévia (MCP) to the municipality before opening. Ask the relevant adviser to confirm which procedures apply to your address and activity.

Lisbon municipal guidance on changes of use · Gov.pt guidance on opening a food or drinks establishment

Give each decision to the right person


Tenant, landlord, design team and contractor each decide different things. Resolve those questions together before asking for a fixed price.
WhoWhat they decide or confirm
Tenant or operatorSet the business brief, budget and opening target. Choose the equipment and approve scope, cost and programme changes. Assign someone to track opening requirements.
Landlord or building managementConfirm the unit’s handover condition, landlord works, building rules and consent for alterations within their control. Identify who else must agree to work affecting shared areas.
Design teamSurvey the space, test the layout and services, assess applicable accessibility and fire-safety requirements, identify approvals and prepare the drawings and specifications for pricing.
ContractorReview how the design can be built, price the agreed scope, identify lead times and dependencies, and carry out the works, testing and handover required by the contract.

An office operator can decide how many meeting rooms they need. The design team checks how the partitions affect ventilation and escape routes. The landlord or building manager confirms what can be changed in shared systems. The contractor prices and programmes the agreed work. Resolve those questions together before asking for a fixed price.

Portuguese accessibility framework · ANEPC guidance on fire safety responsibilities

Not sure what to verify first?
Send Remodel the listing or floor plan and your intended use. We can discuss what to check before you sign the lease.
Discuss your project

Get comparable quotes and plan backwards from opening


Send every bidder the same package, split landlord works from contractor works, and put access, rent start and opening dates on one schedule.

Send each bidder the same drawings, specification and pricing schedule. Split landlord works, contractor works and anything you’re buying separately, such as furniture, kitchen equipment, shop fittings or IT. Ask bidders to state what they’ve included, what they’ve excluded, which figures are allowances, how VAT is shown and when they could start. Check relevant commercial references and verify the contractor’s applicable credentials.

How to compare renovation quotes · IMPIC contractor registers

Put these three dates on the same schedule.

Date 1
The date you get access
Date 2
The date rent starts
Date 3
The date you plan to open

Work backwards from opening through staff setup, equipment installation, testing, snagging and construction. Add the last dates for landlord decisions, design approvals and orders with long lead times. Give each milestone an owner.

For example, if your shopfront can only be ordered after the final measurements and written consent, put both dependencies in the programme. Ask the contractor what can proceed in parallel and what would have to move if consent or delivery slips.

Plan the handover before you announce the opening


Walk the site with the contractor and design team, test the systems you depend on, and close any safe-operation issue before opening.

Walk the site with the contractor and design team. List outstanding items and agree who will close them and by when. Test the systems your operation depends on and collect the applicable commissioning records, certificates, manuals, warranties, keys and updated drawings. Check that the landlord’s handover requirements and any opening procedures assigned to your team are complete.

Leave time between construction handover and opening for stock, furniture, IT setup, staff training or an operational trial. Walk through the first day as a customer and as a member of staff.

First-day walk-through
  1. Can everyone enter, use the space and leave safely?
  2. Can staff operate the equipment?
  3. Who will take the call if a system fails?
Close any issue that affects safe or lawful operation before opening.

Planning an office, restaurant or shop?


The first checks depend on how you will use the space: headcount and ventilation for offices, extraction for restaurants, the shopfront for retail.
Office
Headcount first

Start with headcount, meeting rooms, ventilation, data and the date your team needs to move.

Office fit-outs and commercial renovations
Restaurant
Menu and equipment first

Start with the menu and equipment, then check extraction, deliveries, waste and the proposed customer layout.

Restaurant and hospitality renovations
Retail
Shopfront first

Check the shopfront, signage, customer route, display lighting, stockroom and delivery access.

Shop and showroom fit-outs
Have a property in mind?
Send Remodel the listing or floor plan, intended use, approximate area, current lease stage and target opening date. We can discuss what to verify before asking contractors to price the work.
Discuss your commercial fit-out
Kellogg Fairbank
Kellogg Fairbank
Co-founder, Remodel · Cascais, Portugal

Kellogg is a former payments executive turned entrepreneur, with a family background in real estate. He has spent the past year bringing that experience to the Portuguese property market, and co-founded remodel to apply the same rigor to how contractors are vetted.

This guide gives general information and is not legal, planning or technical advice. Confirm the requirements for a specific property with a local architect, engineer, lawyer or the câmara municipal. Vetting supports informed selection; it does not guarantee future performance or replace project-specific checks, contracts and oversight. You contract directly with the appointed professionals and contractors. Photos are illustrative and do not show a remodel project. Regulatory information checked 11 November 2026.